I stopped trusting the Friday afternoon update meeting after a job in Billings
Everyone on my crew loves the big Friday walkthrough where we sync up the schedule for the next week. I used to sit through those for an hour every Friday and felt like we were on top of things. Then last October we had a job in Billings where the schedule said we were done framing on the 14th, but two of my guys showed up to find the truss delivery hadn't even been ordered yet. That one meeting cost us 6 days and about $4,200 in idle time. Since then I've been doing a quick 10 minute check in on Monday morning instead, and we catch way more of those gaps before they turn into lost days. My PM thinks I'm nuts for skipping the Friday call, but the numbers on our last three jobs don't lie. Anyone else ditch the big weekly sync and go smaller?