Trying to get a permit for a backyard shed in Decatur turned into a six week email chain with the county.

Has anyone else dealt with the zoning office and found a faster way to get a straight answer?
3 comments

Log in to join the discussion

Log In
3 Comments
danielh81
danielh813mo ago
Ugh, tell me about it. I had to call them three times just to figure out which form I needed. The only thing that kinda worked was asking for a supervisor right away. They still took forever, but at least the supervisor gave me a real answer instead of sending me in circles. Honestly, I think they just make it hard on purpose. Good luck, you're gonna need it.
5
martin.jamie
Bringing my paperwork with a checklist of what I needed finally got them to process it in one visit.
3
ninal91
ninal913mo ago
Oh man, that's the worst. Honestly, just show up in person if you can.
1